Lack of electricity is causing AI data center delays

The rapid expansion of artificial intelligence is creating enormous demand for the infrastructure needed to support it. But even as companies commit billions to building data centers, access to a critical resource could determine how quickly these projects move forward. In today’s FA Alpha Daily, we examine why electricity shortages are becoming a major bottleneck for AI infrastructure and what this could mean for companies positioned to meet the growing demand for power.

FA Alpha Daily:
The Monday Macro Report
Powered by Valens Research

Microsoft (MSFT) just walked away from a data center it has yet to build.

The site is in Loughton, a town in Essex, just northeast of London. It’s being developed by Nscale, a British “neocloud.”

Microsoft was supposed to be the site’s main customer. Nscale planned to fill it with more than 23,000 AI chips from chipmaker Nvidia (NVDA) for Microsoft’s cloud business. Then, in October, Microsoft pulled out.

It’s an awkward moment for Nscale. The company is trying to raise as much as $3 billion in an initial public offering (“IPO”), and investors were already nervous about the risks of the AI build-out.

Many investors and observers took this as a sign that the AI infrastructure might be grinding to a halt.

However, these delays come down to lack of electricity, and the companies supplying energy are already filling that demand..

Nscale’s data center was supposed to connect to the local power grid by the end of 2026. Instead, grid officials told the company they don’t expect to supply power until the 2030s. Nscale blamed what it called a London-wide grid issue and said its other contracts with Microsoft aren’t affected.

A data center can’t run on a normal electrical setup. Before it can operate, the local utility has to build or upgrade the substations and power lines that carry electricity to the site. And each new project waits in line behind the ones that asked first.

That line is getting long everywhere. Energy research firm Sightline Climate (now called Currence) tracks large data centers around the world. At the start of this year, it counted at least 16 gigawatts of capacity scheduled to come online in 2026—roughly the output of 16 large nuclear reactors.

Sightline expected 30% to 50% of that capacity to be delayed, up from about a quarter of the capacity planned for 2025. Power shortages and backlogs for electrical equipment top its list of reasons.

Some builders aren’t waiting for the grid situation to improve.

For example, Elon Musk’s AI company, xAI, uses its own gas turbines to power its Colossus data centers near Memphis, Tennessee.

For its second site, Colossus 2, xAI set up 27 gas turbines just across the state line in Southaven, Mississippi. Together, they can produce up to 495 megawatts, about as much as a conventional power plant.

The approach has its critics. Civil rights group the NAACP sued xAI in April for running the turbines without air permits, and a federal judge recently refused to throw out the case. But it let Colossus 2 start running without waiting on the grid.

That’s made xAI a supplier to other AI companies. In May, Claude maker Anthropic agreed to pay SpaceX $1.25 billion a month through May 2029 for computing power. It started at the original Colossus site and expanded into Colossus 2 in June.

Anthropic is also one of Nscale’s biggest customers. Together with Microsoft, it accounts for around 85% of Nscale’s contracts. So one of the AI companies behind Nscale’s contract book is already buying from a builder that had its power in place.

In short, what’s playing out isn’t a demand problem.

The grid isn’t adding power as fast enough to power the AI data centers being built. This means more headlines about stalled data centers.

So when the next headline hits, it’s better to look at why the project got delayed in the first place. If the culprit is a grid connection, then it means the customer still needs computing power.

And just as Anthropic did with xAI, the customer will work with who can deliver it the soonest.

This setup also benefits the companies that can help provide power or help data center operators generate the electricity they need.

Best regards,

Joel Litman & Rob Spivey
Chief Investment Officer &
Director of Research
at Valens Research

Today’s analysis only scratches the surface of what we share with our FA Alpha Members. If you want to gain an in-depth analysis of market trends and uncover undervalued stocks, become an FA Alpha Member today.

Subscriptions & Services

FA ALPHA DAILY | FREE

Get FA Alpha Daily free

One company or signal each weekday, with the Uniform Accounting numbers beside the as-reported ones.

Free. Unsubscribe anytime.

FA ALPHA DAILY | FREE

Before you go, get FA Alpha Daily free

Each weekday we take one company or market signal and put the Uniform Accounting numbers beside the as-reported ones. A few minutes to read. No credit card.

Free. Unsubscribe anytime.

Please fill out the fields below so that our client relations team can contact you.

Or contact our Client Relationship Team at +1 630-841-0683